Poinsett Highway Was Rebuilt to Be Travelers Rest's Second Downtown Street

In the third week of August, Emma Bradford noticed a change behind the counter at Leopard Forest Coffee Company. Both lanes of North Poinsett Highway had just reopened after months of detours. "This week we've already seen tremendous growth since both lanes of the road are now opened," the longtime barista told WYFF.

Six weeks later, on Thursday, October 1, the City of Travelers Rest held a grand reopening and declared the Poinsett Highway Streetscape Project complete. City officials put the cost at more than $9 million, according to WSPA. That is a lot of money for a road that is still two lanes, and the design explains it. The city spent the money to turn Poinsett into a second downtown street.

"Away From a Linear One Street"

City Administrator Shannon Herman described the goal plainly at the reopening. "This was really the opportunity to move away from a linear one street, Main Street, into more of a geometric central business district and so this is it. We're here," she told WSPA.

Ten months earlier, while crews were still in the ground, she spelled out the commercial logic to the same station. She called Poinsett "the critical link for our central business district between the 25 interchange and downtown." She said Main Street covers "your tourism and day to day activities," while the Poinsett corridor gives the city room to attract businesses that "don't necessarily need to sit on the street."

The City's project page describes the corridor the same way, as "a key commercial hub within the City's Central Business District," running between Main Street and State Highway 25. Every element below fits that goal of making Poinsett a place where people stop, park and walk, the way they already do on Main.

What Was Actually Built

On the City's list, the finished corridor includes:

  • A two-lane roadway, kept at two lanes on purpose
  • A 10-foot multimodal path on one side for walking and biking, plus a 5-foot sidewalk on the other
  • Planting strips separating both paths from traffic
  • Parking lots behind businesses, so storefronts can face the sidewalk
  • A pedestrian crosswalk from the lot across from Chicora Alley
  • A traffic and pedestrian signal at Tubbs Mountain Road and Poinsett Highway
  • Stormwater management, resurfacing and ADA-compliant sidewalks

Most of the money went to the part nobody sees. "The road is really old, and it was a flat road, which is not how we build roads these days because of water movement," Herman told WSPA in December 2025. "So, we've built in a crown. We built in the storm drainage. We've lifted it up." At the reopening she said it "took a year to get the road into condition," and pointed to deep digging, utility relocation and stormwater improvements as the heavy lifting.

The lighting is also designed for people on foot. The City's August 2026 newsletter describes new solar streetlights along South Poinsett that dim when nobody is around and brighten as pedestrians, cyclists or cars approach. A road built only for commuting doesn't need lights that respond to someone walking to dinner.

How Long It Took

The schedule ran well past the city's own estimate. Here are the milestones the City and local TV reported:

When What happened
March 3, 2025 Traffic-impacting work begins between Tubbs Mountain Road and Hart Street, with one-way traffic
March 11, 2025 City reports curb, sidewalk and gutter work complete from Hart Street to Tubbs Mountain Extension
July 2025 Active work on a roughly half-mile North Poinsett segment from Center Street to Mustang Drive
Winter 2025 City says the project remains "on schedule for completion in early 2026"
Spring 2026 Northbound lane reopens and repaved; southbound lane closes with detours
Summer 2026 Both lanes fully open; sidewalks, curb, gutter and driveways complete
October 1, 2026 Grand reopening; City declares the streetscape project complete

"Early 2026" turned into an August lane reopening and an October ceremony.

The Businesses That Stayed Open Through It

Throughout construction, the City repeated that every business would remain open and accessible, and asked drivers to follow detour signs. At Chicora Alley Fire House, co-owners Greg Gimpel and Smiley Miles told WYFF that loyal customers kept coming through the construction. "It's the friendships and relationships that we build here. More than the food and the beverage," they said. Gimpel's hope for the rebuilt road was simple: "Hopefully we're so busy we can't even talk about it."

These are the corridor businesses listed in the City's 2026 dining and shopping directories:

Business Address What it is
Chicora Alley Fire House 117 N. Poinsett Hwy. Local bar and restaurant, beer and full meals
Swamp Rabbit Gear & Spin 206 N. Poinsett Hwy. Outdoor-gear consignment and local makers shop
Wild Hare Gallery 212 B N. Poinsett Hwy. Local art and fine crafts
Sunset Slush of Travelers Rest 223 N. Poinsett Hwy. Italian ice, smoothies and fresh juices
Leopard Forest Coffee Company 403 N. Poinsett Hwy., Ste. D Coffee shop
Glade Salon & Day Spa 27 S. Poinsett Hwy. Full-service Aveda salon and day spa

Taken together, that's coffee, dinner and drinks, a frozen treat, an art gallery, gear and a spa, all on the stretch the city rebuilt. With parking lots behind the shops and a 10-foot path out front, the corridor is now built for parking once and walking between stops, the way people already use Main Street.

Where the Two Streets Meet

The second street only works if it connects to the first, and the city put work into the joints.

At Main Street and Center Street/McElhaney Road, a diagonal bicycle crossing lets cyclists cross the intersection in one movement while pedestrians use marked crosswalks. The City lists it among the Poinsett project's benefits and also describes it separately as a crosswalk project. WSPA's reopening coverage counted it among the changes, along with the new signal at North Poinsett and Tubbs Mountain Road. The City's July 2026 newsletter reported that signal was already working.

The project list also includes a left-turn lane onto North Main Street from Center Street. In its Winter 2025 update, the City described a new all-stop crosswalk at McElhaney Road and Main Street near Sunrift Adventures to give Swamp Rabbit Trail users a safer crossing.

One more Main Street change is in progress. The City's August 2026 newsletter, posted September 4, said it had started moving the Main Street crosswalk from near the Gazebo to near the Pinestone walkway, with lighted pedestrian signals planned on both sides of the street. That update described the work as underway. As of mid-October, no source we found has reported it finished.

What Fills In This Fall

The City has declared the project complete, but its own updates left one piece for cooler weather. The Summer 2026 update said final landscaping, including trees and plants, would go in "once fall temperatures are favorable." Those planting strips may stay bare a while longer, and they will fill in over the coming weeks and seasons.

The commercial side will take longer. Herman pitched the corridor as room for businesses that don't need a Main Street storefront. The six businesses in the table stayed open through roughly a year and a half of construction, and the rear parking lots and wider paths are there now for whoever opens next.

If you've been driving straight past Poinsett Highway out of habit since the detours, this fall is a good time to stop at Leopard Forest, Chicora Alley or Wild Hare Gallery. And if you're curious how changes like this affect life and property close to downtown Travelers Rest, I'd be glad to talk it through. Ashley Swann follows these corridor projects closely. Let's Connect.