"We've spent the last 15 years working on this project and from the beginning it has been objectively ranked, in the GPATS planning document and the SCDOT environmental assessments, as the highest priority project in the region," Keith Brockington, transportation manager for the Greenville-Pickens Transportation Study, told The Greenville News in October.
That priority now has funding behind it. Keeping it funded meant setting other projects aside, and two of them are in Five Forks. If you're comparing Five Forks with other Upstate suburbs and someone mentions Woodruff Road traffic, here's how it works out. The big regional fix ends west of the Five Forks crossroads. Paying for it delayed the smaller projects inside Five Forks itself, and both of those effects play out over the next seven years.
The project that moved to the front of the line
The SCDOT Woodruff Road Congestion Relief Project is a new five-lane, limited-access road running parallel to Woodruff Road. It goes from Verdae Boulevard to Smith Hines Road and includes a median, a sidewalk, a multi-use path, and new bridges over I-85 and I-385. SCDOT describes it as an extension of the Piedmont Natural Gas Connector, now called the Woodruff Road Bypass, running from Woodruff Industrial Road to Smith-Hines Road.
The Greenville News reported that the corridor carries more than 40,000 vehicles a day at peak times, according to SCDOT. That volume is why the project has ranked first in the region for so long.
The problem was cost. Inflation more than doubled the estimate, from $130 million to $277 million, according to GPATS figures cited by The Greenville News. GPATS had already spent federal money on engineering, environmental work and right-of-way, so dropping the project wasn't a realistic option. In August 2026, the GPATS Policy Committee decided that other road projects would wait instead. Brockington's case for moving fast was that stretching the funding out would have added roughly another $30 million in inflation alone.
The October 12, 2026 GPATS agenda packet lays out how that works on paper. It sets aside $28.409 million in FY2027 for clearing and grubbing and $50.968 million in FY2029 for the main construction phase. Another $115.713 million in construction money is pulled forward into FY2029, and SCDOT advances $10 million in FY2032, to be repaid in FY2033.
Where the money came from
Moving that money to Woodruff Road delayed at least 17 other GPATS projects, The Greenville News reported, and most of them now wait until funds open back up, likely around 2033. The GPATS minutes sort them into two groups: projects that are delayed and projects that are removed "for now." Five Forks has one in each.
| Project | What it would build | Status before the August 2026 change | Status now |
|---|---|---|---|
| Garlington Road | Corridor improvements from SC-146 to Roper Mountain Road | Estimated completion FY29 | Funding not available until 2032; construction to begin after the Woodruff Road project is completed |
| S-164 Batesville Road Phase II | Widen to three lanes with curb, gutter and sidewalks, Pelham Road to the Parkway | On hold; right-of-way moved to FY2028, construction letting to FY2030 | Removed from the program "for now" |
Garlington Road now has a defined place in line, behind the bypass. Batesville Road Phase II has no new date at all. The packet ties the restart of the whole program to FY2033, when GPATS expects to "have funds to begin adding projects back into the program." That year marks when money becomes available. It doesn't commit to any particular road.
Greenville County Council chairman Benton Blount summed up the trade-off for The Greenville News: "I don't like having to put multiple projects off, because there's probably a lot of other need in those areas, but I do understand the necessity to prioritize it."
Batesville Road was waiting on a highway that stalled
Batesville Road Phase II was already stuck before the Woodruff Road money moved. The GPATS status report says right-of-way work moved to FY2028 and construction to FY2030 "due to the uncertainty of the I-85 widening project," with funding to be adjusted "when there is a clear path forward."
The widening behind that hold was SCDOT's plan to add a fourth lane in each direction on I-85 from near SC-153, Exit 40, to near SC-85, Exit 69. Fox Carolina reported in April 2025 that the construction start had moved from 2026 to 2030. A week later, The Greenville News reported that SCDOT had shelved the plan. In its place, the AASHTO Journal reported in December 2025 that SCDOT planned a 2026 planning-level study of 35 miles of I-85, from US 29 at Exit 34 to SC 85 at Exit 69, covering 18 interchanges.
So a local road in Five Forks has been waiting on decisions about an interstate, and that interstate has gone from a widening plan to a corridor study. When the August restructuring removed Batesville Road Phase II from the program, it formalized a pause that had started earlier. WSPA named Batesville Road improvements back in May 2026 as one of the projects that could face funding shortfalls.
The next decade, year by year
Lay the schedules side by side and Five Forks' place in the order is clear. This is the sequence as of November 2026:
- Spring 2027. SCDOT advertises bids for Phase I of the Woodruff Road project: clearing, grubbing and demolition.
- Summer 2027. Phase I work begins and is expected to take about 18 months. Roadway construction follows.
- Fall 2029. SCDOT's project page lists Phase II construction.
- 2032. Brockington told The Greenville News that some sections of the bypass could open. Garlington Road funding also becomes available that year.
- 2033. The bypass is set to be substantially complete, and GPATS expects funds to start adding delayed projects back.
- 2034. GPATS records final construction as complete.
Garlington Road construction starts only after the bypass is finished. Batesville Road Phase II comes up only if it's added back once that 2033 money opens. For anyone buying in Five Forks this winter, that covers about seven years of ownership. In that time, the Woodruff corridor near I-385 will have a construction zone and then a new parallel route, while the main local roads inside Five Forks keep their current layout.
What Five Forks already got
The same GPATS program has already finished work in Five Forks. Its project pages describe "substantial work" completed on the Woodruff Road widening from near Scuffletown Road to Bennetts Bridge Road. They say the same about the Batesville Road widening between SC-14 and Roper Mountain Road.
That's useful context for a buyer. The stretch of Woodruff Road through the Five Forks commercial area is mostly the finished version, and the earlier Batesville segment is too. What's still pending sits at the edges, on Garlington toward Roper Mountain and on Batesville between Pelham Road and the Parkway. Today's traffic on those segments is what the published schedules leave in place for years.
That makes a commute test straightforward. If a home you're considering means a daily drive on Garlington Road, or on Batesville between Pelham and the Parkway, drive it at the hours you'd actually use it. The published schedules hold those roads as they are until the bypass is finished. If your route runs west on Woodruff past I-385, expect construction there in the years before the new road opens.
FAQ
Does the Woodruff Road Bypass reach the Five Forks crossroads? No. SCDOT's limits run from Verdae Boulevard to Smith Hines Road, with bridges over I-85 and I-385.
Which projects kept moving through the restructuring? Projects that had already started preliminary engineering are continuing: East Butler Road, Rutherford Road at North Pleasantburg Drive, and Haywood Road at Pelham Road, The Greenville News reported.
Could the delayed projects come back sooner? GPATS plans to apply for a federal BUILD grant in 2027, ideally $50 million, to offset costs and restore many or all of the affected projects, according to the October packet.
If you're deciding between Five Forks streets and the daily drive is part of the decision, I'm happy to go through these road schedules with you for the homes you're considering, from the routes you'd use to where they sit in the construction timeline. Ashley Swann can help you see what the next decade of roadwork means for each address. Let's Connect.